Dauphin Humanities Center Renovations
Started: April 2007
Completion: June 2008 Heiges Field House

Elevator Refurbishment
Start: May 2008
Completion: June 2008

Replace Arena Air Handling Units
Start: May 2008
Completion: August 2008 New Campus Entrance
Start: May 2008
Completion: August 2008 Rowland/Shearer Exterior Repointing
Start: June 2008
Completion: August 2008 Shippen Hall Window Wall Replacement
Start: May 2008
Completion: June 2008 Burd Run Bridge Replacement
Started: March 2008
Completion: August 2008 Reisner Dining Hall Addition & Renovation
Started: February 2008
Completion: August 2009 Ezra Lehman Library Circulation Area Renovation
Start: May 2008
Completion: August 2008 Gilbert Hall ADA Bathroom Construction
Start: July 2008
Completion: August 2008 Overlay Route 696
Start: July 2008
Completion: July 2009 Seth Grove Stadium Repair and Replace Asphalt
Start: August 2008
Completion: September 2008 MCT Roof Repairs
Start: May 2008
Completion: August 2008 Kriner Dining Hall Replace Shingle Roof
Start: May 2008
Completion: August 2008 Rife Alumni House Replace Garage Roof & Replace Stone Walkway
Start: May 2008
Completion: August 2008 Seavers Apartments Regrout Showers
Start: May 2008
Completion: August 2008 Multi-Use Field Fence Relocation
Start: August 2008
Completion: September 2008