Resurface front of Seth Grove stadium bleachers

Resurface north end of stadium to several feet beyond/outside ticket booths

Drainage improvement and resurface back of north end
Pave existing gravel area located behind stadium at south end
Project includes a combination of asphalt removal, repair, and overlay of asphalt. Depending on location one or all of these processes will be worked. A trench drain is planned for drainage improvement.
Tentative schedule for planned work is mid June 2008, following Relay for Life weekend.